The Renovation of Nicosia’s Makarios Avenue III Commenced

After the completion of Phase A of the reconstruction project of the commercial triangle Makarios - Stasikratous - Evagorou and the delivery of Stasikratous, Zina Kanther, Theofani Theodotou and Mnasiadou streets (section) to the public, the Municipality of Nicosia has proceeded with the implementation of the next phase of this important project.

Phase B of the project concerns the section of Makarios Avenue from its junction with Spyros Kyprianou Avenue to Evagorou Avenue, Anastasiou G. Leventi Street, sections of Stasandrou and Aphrodite Streets and Arnaldas, Agia Eleni, Xenopoulou, Bouboulinas, Iras and Annie Komninis, until their contribution to Stasandrou Street.

The budget of Phase B of the project amounts to EUR11,680,000 plus VAT, and the construction work for the entire Phase B is expected to last a total of about 26 months. Due to the large area of the intervention area and to reduce the suffering of the public, Phase B of the project will be implemented in smaller sections.

The construction works in the first period (Phase B.1) has already begun on July 13, and will focus on the section of Makarios 'Avenue from its photo-controlled contribution with Spyros Kyprianou Avenue to its photo-controlled contribution with Aphrodite / Stasandrou, in which the movement of vehicles will not be allowed. The duration of Phase B.1 will be 13 months.